Managing a Project-Based Cash Flow Crisis at a Construction Firm

Company Profile

A firm running five concurrent residential and commercial projects managed cash largely at the portfolio level, as a single pool, without distinguishing between projects.

Situation Assessment

When a progress payment on a major project was delayed four months longer than expected, that single project's cash shortfall put supplier payments on the other four projects at risk too — because all cash was managed in one pool, and which project was actually in trouble was not visible at first glance.

Strategy Applied

A three-phase approach brought visibility down from the pool to the project level:

Phase 1: Project-Level Cash Segregation

Cash inflows and outflows began to be tracked separately for each project; this made clear that the problem belonged to a single project, not the whole portfolio.

Phase 2: A 13-Week Rolling Forecast

Rather than a short-term view, a cash forecast model looking thirteen weeks ahead was built; this surfaced a potential shortfall weeks before it would actually occur.

Phase 3: Pre-Negotiated Flexibility

Flexible payment schedules to be activated in the event of a delay were negotiated with critical suppliers in advance, not in the middle of a crisis.

Results and Impact

After eleven months, the firm managed the crisis without missing a single supplier payment. The 13-week cash forecast model continued to be used as a standard management tool even after the crisis ended.

Lessons Learned

Managing multiple projects out of a single cash pool conceals the source of a problem and allows a crisis to spread across the entire portfolio. Project-level visibility and forward-looking forecasting are the two most fundamental tools for making a cash crisis manageable.