Managing Contract Risk Early at a Construction Firm

Company Profile

A firm working on public infrastructure and road projects frequently encountered situations falling outside contract scope due to the variability of field conditions.

Situation Assessment

Situations such as an unforeseen rock layer in the soil survey or a revision the authority made to the project scope imposed additional cost on the firm; but the timely, correct documentation needed to claim these costs under the contract was usually not done. Because field teams prioritized keeping work moving over stopping it, documenting an event the moment it happened was neglected.

Strategy Applied

A three-phase path turned a legal matter into an operational habit:

Phase 1: Immediate, Standard Documentation

Field teams were trained to document every out-of-scope situation the moment it occurred, with photos and a standard form.

Phase 2: A Forward-Looking Risk Register

A risk register was introduced for each project, listing likely claim situations in advance based on past experience.

Phase 3: A 48-Hour Rapid Assessment

A process was set up between the legal and technical teams to carry out an initial assessment within 48 hours of an event being reported; this ensured documentation quality was checked while the event was still fresh.

Results and Impact

After ten months, the firm successfully collected a significant share of claim amounts it would previously have lost. The documentation habit among field teams became a lasting practice even after the project ended.

Lessons Learned

In construction contracts, claim rights largely lose their value if noticed months later rather than at the moment of the event. Field teams being able to immediately ask is this something that needs documenting turns a legal matter into an operational habit.